- Home
- Residents
- Current City Projects
- Recreation & Aquatic Center Project
Recreation & Aquatic Center Project
CONSTRUCTION UPDATES:
October 2023
See the following for the construction highlights completed during the month of October:
- Mechanical roof work is ongoing
- Completed metal roofing for Gymnasium and Natatorium
- Poured cantilevered gutter at the natatorium
- Installed Community Lounge windows
- Installed basketball hoops at the gymnasium
- Poured transformer pad
- Completed seat wall at entrance
- Completed outdoor lap pool lane tiling
- Completed landscaping at the creek including the creek bioswales
- Completed Pool Chemical Room grading and foundation
September 2023
See the following for the construction highlights completed during the month of September:
- Ongoing/In Progress
- Low roof installation
- Interior insulation and drywall installation
- Outdoor pool tiling installation
- Landscaping at the creek
- Completed gymnasium and Community Hall Roof
- Completed exterior insulation foam system in the gymnasium
- Window installation ongoing
- Stone Veneer attached at the North Side exterior
- Installed railing for the Community Lounge and Natatorium stairs
- Placed scaffolding in the natatorium for sandblasting trusses and other ceiling work
- Installed Dehumidification Unit
- Completed outdoor pool and wading pool gutter, surge tanks, and steps
- Completed irrigation work
- Subgrade for pathways to pedestrian bridges
- Installed bioswale liners
August 2023
See the following for the construction highlights completed during the month of August:
- Completed flat roof
- High roof insulation in progress
- Coordinated solar panel layout
- Continued exterior insulation foam system
- Window installation ongoing
- Completed stone veneer attachment clips at the north side
- Continued interior insulation and drywall installation
- Worked on community lounge and natatorium stairs
- Painted main electrical room
- Continued work on indoor pool deck plumbing
- Cured outdoor pool shell
- Completed wading pool plumbing
- Irrigation work ongoing
- Installed wading pool water cannons
- Mounted pedestrian bridges
- Cleaned up bioswale
- Worked on PG&E trenching, substructures, and conduits inspected
July 2023
See the following for the construction highlights completed during the month of July:
- Indoor Pool shell curing
- Sprayed exterior wall waterproofing
- Continued external wall framing and sheathing of mechanical roof
- Began roof insulation work
- 95% complete with mechanical, electrical, and plumbing installation at the gymnasium
- Completed broadcasting capability for design coordination
- Continued outdoor pool bottom and wall rebar
- Continued outdoor pool shell curing
- Continued outdoor pool piping backfill
- Progressed with wading pool excavation
- Completed creek repair and modification
- Completed soft soil work in the parking lot
- Began PG&E trenching, substructures, and conduits
June 2023
See the following for the construction highlights completed during the month of June:
- Began exterior wall sheathing installation at the gymnasium
- Worked on exterior soffit framing
- Poured bottom of indoor pool shell
- Poured mechanical roof curbs and insulation
- 90% complete with Mechanical, Electrical, and plumbing installation at the gymnasium
- Completed outdoor pool plumbing
- Began creek repair and modification
- Completed domestic water installation with thrust block and kicker
May 2023
See the following for the construction highlights completed during the month of May:
- Worked on under pool plumbing for the indoor pool
- Continuing indoor pool wall rebar
- Continuing wall framing within the natatorium
- Worked on insulation of refrigerant piping in the gymnasium, interior and exterior wall framing
- Completed storm, sewer, and fire water around the outdoor pool, except for storm piping at the outdoor pool retaining wall
- Worked on outdoor pool excavation
City Park Way was closed to traffic on Friday, May 19, 2023 from 7AM-3PM to off haul surplus soil. Signage was displayed in and around the area with the planned closure and appropriate temporary detour signage was posted.
April 2023
See the following for the construction highlights completed during the month of April:
- Started indoor pool excavation and pool plumbing
- Completed trench restoration at Crystal Spring and Desoto Way
- Continue exterior wall framing
- Continue mechanical, plumbing, electrical and HVAC work
- Start masonry wall installation at natatorium
- Prep work at parking lot
- Continue onsite drainage and utility installation
- Continue off-haul of contaminated soil
City Park Way was closed to traffic during the following days/times to off haul surplus soil. Signage was displayed in and around the area with the planned closure and appropriate temporary detour signage was posted.
- Thursday, April 13, 2023 (7AM-4PM)
- Friday, April 14, 2023 (7AM-4PM)
- Monday, April 17, 2023 (7AM-4PM)
- Tuesday, April 18, 2023 (7AM-4PM)
March 2023
See the following for the construction highlights completed during the month of March:
- Continued exterior wall framing
- Continued HVAC duct installation
- Continued electrical rough-in
- Framed interior wall (Group Exercise Room)
- Poured concrete on stairs (To Locker Rooms from Main Lobby, To Locker Rooms from Gymnasium, To 2nd floor from Pool Lobby)
- Poured (Line 1) concrete wall
- Poured first floor concrete slab in multiple rooms (pulp room, pool storage, men's & women's restroom, party rooms 1 & 2)
- Continued storm water and site management
- Continued parking lot rough grade
February 2023
See the following for the construction highlights completed during the month of February:
- Worked on first floor concrete slab at the Natatorium
- Continued first and second floor mechanical, electrical, and plumbing work
- Continued with HVAC duct installation
- Continued gymnasium first and second floor wall framing
- Continued fire sprinkler risers, laterals, and heads throughout gymnasium
- Installed exterior walls sheathing
- Continued parking lot grading
January 2023
See the following for the construction highlights completed during the month of January:
- Completed fire sprinkler pipe materials inspection
- Installed first floor and second floor overhead plumbing, mechanical hangers, and fire sprinklers pipe
- Installed second floor wall framing, primarily near the community hall and community hall kitchen
- Lengthened rock truck access/driveway for vehicle access around the site
- Started parking lot grading
December 2022
See the following for the construction highlights completed during the month of December:
- Completed Gymnasium concrete slab form and pour
- Continued structural welding & plumbing of building steel & metal decks
- Completed second floor slab partial concrete pour
- Prepare for exterior walls installation
- Continued mechanical, electrical, and plumbing installation
- Continued roadside curb, gutter and paving
- Reopened City Park Way to vehicular traffic on the afternoon of December 23, 2022
November 2022
See the following for the construction highlights completed during the month of November:
- Rebar, formwork, and concrete pour for curbs and gutters on City Park Way
- Contractor completed the new 10” water line tie from Crystal Springs to De Soto
- New sewer pipe was installed under the culvert between SSMH3 and SSMH4.
Installation of street lighting started, pole bases dug - Structural welding and plumbing of building steel continued
- City inspection of rebar and concrete pour of 2nd floor topping slab
- 2nd floor wall layout started
October 2022
See the following for the construction highlights completed during the month of October:
- Rebar, formwork, and concrete pour for bioretention walls
- Installed a 10” water line
- Installed creek winterization
- Backfill of new fire water and installation of an offset manhole/storm drain
- Structural welding and plumbing of building steel and metal decks continue
- Continue forming column block outs before slab rebar and pouring
September 2022
See the following for the construction highlights completed during the month of September:
- Epoxy rebar at shotcrete wall Gridline A
- Natatorium trusses and steel erection, the start of Epic metal decking on both buildings
- 8” PVC conduit under creek for future solar
- Storm drain and new main water piping on City Park Way
- Compaction testing for backfilling of utilities on City Park Way
- Final grading at the creek, backfill of low flow materials, cobble, and large rock
August 2022
See the following for the construction highlights completed during the month of August:
- Installed underground plumbing and electrical, backfilled utility trenches
- Backfill foundation and compaction testing
- Cofferdam and bypass installed, dewatered creek
- Natatorium and gymnasium steel erection, the start of metal decking
July 2022
See the following for the construction highlights completed during the month of July:
- Completed concrete pours of natatorium and gymnasium foundation
- In process of installing underground plumbing, electrical, and backfilling utility trenches
- In process of backfilling foundation, compaction testing
- Installed exclusionary fencing and bypass for creek extension
- Started 10" waterline with polyethylene encasement on Crystal Springs Road
City Park Way Temporary Closure: August 2022 - December 2022
Beginning August 1, City Park Way was closed to vehicle and pedestrian access. The road closure was necessary to install the deep utilities (Water, Sewer and Storm), creek and road reconstruction, and other construction activities related to the Recreation and Aquatic Center Project. City Park Way was closed through December 2022.
Park patrons accessed the park through the pedestrian pathways located:
- near the north end of De Soto Way (the former pool parking lot)
- near Tom Lara field
- near the rear of baseball diamond #2
- near the west end of San Felipe Avenue
Vehicle traffic could not access City Park Way at Crystal Springs/Oak. Vehicle traffic was detoured down to El Camino Real, and up Santa Lucia Avenue to access the former pool parking lot. Please use caution in and around the area, and we appreciate your patience as we build our new community facility!
City Park Way Road Closure - Vehicular Detour Map
June 2022
See the following for the construction highlights completed during the month of June:
- Completed excavation for building foundations
- Completed rebar reinforcement for foundations at natatorium, near-complete at the gymnasium.
- Fencing and exclusionary fencing installed for creek restoration.
- Grading started for the creek.
- Starting 10” waterline on Crystal Springs Road
Water Line Installation: The new Recreation and Aquatic Center Project's water line installation occurred from June 27 through approximately July 29, 2022. The construction work took place between the hours of 8:00AM and 5:00PM, Monday through Friday.
Traffic along Crystal Springs Road was limited to one-lane of traffic near City Park Way. Safety flaggers will be onsite during construction helping with traffic flow in the modified areas. Questions? Contact Us.
May 2022
Construction activity underway at San Bruno City Park, City Park Way and Crystal Springs Ave. Lathrop Construction installed temporary construction fencing at the above noted locations to facilitate continued construction activities for the New Recreation and Aquatic Center Project. In late June 2022, City Park Way closed to vehicular and pedestrian traffic. Crystal Springs Ave. will have periodic lane closures and traffic control will be implemented to allow for utility work. Road closures will be posted on changeable message boards near the work zones prior to start of work.
The site work hours are 7:00AM and 6:00PM, Monday to Friday.
See the following for the construction highlights completed during the month of May:
- Completed second phase of shoring wall
- Certified building pads
- Started excavation for building foundations
- Started placing rebar for building foundations
April 2022
See the following for the construction highlights completed during the month of April:
- Started second phase of Shoring Wall
- Rough graded building pads
- Started and completed GeoPiers work at building pads
- Started and completed crosswalk/sidewalk improvements at south edge of park
March 2022
See the following for the construction highlights completed during the month of March:
- Grading completed at Soil Nail Shoring Wall
- Drilling and setting of soil nails completed at Soil Nail Wall
- Completed grouting of Soil Nail Wall with shot-crete
February 2022
See the following for the construction highlights completed during the month of February:
- Grading continues for Soil Nail Shoring Wall
- Drilled and set soil nails at Soil Nail Wall
- Grouted of Soil Nail Wall with shot-crete (concrete)
- Backfilled old pool excavation
January 2022
See the following for the construction highlights completed during the month of January:
- Removed additional trees along Crystal Springs Road
- Completed 10'' waterline bypass with concrete collars and thrust blocks
- Removed old waterline pipe
- Began grading slope for Shoring Wall
December 2021
See the following for the construction highlights completed during the month of December:
- Abatement completed, final report being developed
- Trees identified for removal in January 2022
- Contractor poised to install temporary water bypass line (delayed due to inclement weather)
- Stoned construction entrance has been installed to limit tracking mud
- Existing streetlights re-energized
November 2021
See the following for the construction highlights completed during the month of November:
- Gym Building Demolition Completed
- Tree Removal along Crystal Springs Road and within San Bruno City Park
October 2021
See the following for the construction highlights completed during the month of October:
- Pool Building Demolition Completed
- Gym Building Demolition Ongoing
- CM Trailer Onsite and Occupied
- Sidewalk closed along City Park Way
- Ramp from Crystal Springs Road to City Park Way closed
September 2021
See the following for the construction highlights completed during the month of September:
- Contractors trailer placed in parking lot
- Abatement
- Perimeter fence installed
- Sidewalk closed along City Park Way
- Ramp from Crystal Springs Road to City Park Way closed
- Partial tree removal performed
- EarthCam site camera installer
If you have any questions or concerns, contact us at RecCenterBuild@sanbruno.ca.gov.
-
Advisory Committee
-
Contact Us
-
Frequently Asked Questions (FAQs)
-
Presentations
Access the current conceptual design in archived presentations.
-
Project Timeline
-
Temporary Location
-
Watch LIVE